API 6A "QUALITY CONTROL REQUIREMENT API 6A PSL 3 TO PSL3G AND PSL 4"

 QUALITY CONTROL REQUIREMENT API 6A PSL 3 TO PSL3G AND PSL 4

Quality Control Requirement as per API 6A 19th Edition

 

No

Equipment

Remark

1

Wellhead, Bonnet and other pressure containing bodies

(Table 11) PSL 1, 2, 3/3G, 4

2

Stem

(Table 13) PSL 1, PSL 2, PSL 3, PSL 4

3

Valve Bore Sealing Mechanism

(Table 14) PSL 1, PSL 2, PSL 3, PSL 4

4

Ring Gasket

(Table 15) PSL 1, PSL 2, PSL 3, PSL 4

5

Stud and Nut

(Table 16) PSL 1, PSL 2, PSL 3, PSL 4

6

Non Metallic Sealing Material

(Table 17) PSL 1, PSL 2, PSL 3, PSL 4

7

Assembled Equipment

(Table 20 – Full Bore Valve) PSL 1, 2, 3, 3G, 4

(Table 22 – Check Valve) PSL 1, 2, 3, 3G, 4

(Table 23 – body, bonnet, tree cap) PSL 1, 2, 3, 3G, 4

(Table 24 – X’mas Tree) PSL 1, 2, 3/3G, 4

8

Mandrel Hanger

(Table 25) PSL 1, PSL 2, PSL 3, PSL 4

9

Bull Plug, VR Plug & BPV

(Table 26) One requirement for all PSL

 Upgrading from PSL 3 to PSL 3G and PSL 4

 

Description

 

 

PSL 3G Requirement

 

PSL 4 Requirement

 

Wellhead, Tubing Head Adapter, Tee, Cross, Tree Cap, Cross Over Connector, Adapter and Spacer Spool, Flanged Connector, Threaded Connector, Other End Connector

 

 

PSL 3 requirement and PS-116 (gas test)

 

PSL 3 requirement and PS-101 (UT) for PSL 4 or PS-109 (radiographic test) for PSL 4 and PS-116 (gas test) and no welding except PSL 3 weld overlay

 

Mandrel Hanger

 

N/A

 

PSL 3 requirement and PS-101 (UT) for PSL 4 or PS-109 (radiographic test) for PSL 4 and no welding except PSL 3 weld overlay

 

 

X-Mas Tree

 

 

PSL 3 requirement

 

PSL 3 requirement

 